LABOR COSTS

1. For Contractor Manufacturing:
Enter a “Part” called CUT, one called SEW, etc.
Make the Unit Value 1.000, and the Unit of Measure “$”.
Click the “For Cost Only” Checkbox.
Category should be Labor.
You might want to begin all Labor Codes with a “W” to keep them together. We use W for Work (L for Labor gets mixed with L for Labels).
On the Components window, assign the $ quantity for the correct cost.
Parts.jpg

Used_In.jpg

2. For In House Manufacturing:
Enter a “Part” called CUT, one called SEW, etc.
Make the Unit Value 1.000, and the Unit of Measure “Hr”.
As above, on the Components window, assign the Hrs quantity to the item.

Back to Top